Tons of gravel for each layer of a driveway (base, middle and top), with fabric and cost.
4–6 in of large stone over fabric.
3–4 in of 3/4–1 in stone.
2–3 in of crusher run or #411 that packs hard.
all three layers, 10% extra included
- Base stone (#3/#4)
- 19.8 tons
- #57 stone
- 19.8 tons
- Crusher run top
- 20.6 tons
- Total depth
- 11 in
- Driveway fabric (10% overlap)
- 147 sq yd
How it works
Tons per layer = length × width × depth (ft) ÷ 27 × weight per cubic yard ÷ 2,000
Example: Driveway length 100 ft · Driveway width 12 ft · Base layer (#3 or #4 stone) 4 in · Middle layer (#57 stone) 4 in · Top layer (crusher run) 3 in · Extra 10% → 60.2 tons (base stone (#3/#4): 19.8 tons, #57 stone: 19.8 tons, crusher run top: 20.6 tons, total depth: 11 in, driveway fabric (10% overlap): 147 sq yd).
A lasting gravel driveway is built in layers over landscape fabric: large base stone (#3 or #4) that carries the load, a middle layer of #57 stone, and a top of crusher run that packs into a hard, smooth surface. Quarries usually recommend 8 to 12 in in all.
For a 100 × 12 ft driveway (1,200 sq ft), 4 in of base stone is 14.8 cubic yards, about 18 tons; 4 in of #57 another 18 tons; and 3 in of crusher run 11.1 yards, about 18.7 tons. With 10% extra, plan on about 60 tons in all. Stone weights run from about 1.2 to 1.4 tons per cubic yard, so ask your supplier for their figure.
Crown the surface so water runs off to the sides, and compact each layer. Penn State's Center for Dirt and Gravel Roads notes that 6 in of loose surface aggregate compacts to about 4.5 in, so the extra matters.
Questions
How much gravel for a 100 ft driveway?
About 60 tons for 12 ft wide in three layers (4 + 4 + 3 in), with extra.
How deep should a gravel driveway be?
About 8 to 12 in in all, in two or three compacted layers.
What gravel is best for a driveway top?
Crusher run or #411, which pack hard; #57 drains well in the middle layer.